By Zorawar Almeida.
Zorawar Almeida is a Research Scholar at the Milon K. Banerji Arbitration Centre.
The Supreme Court in Municipal Corporation of Greater Mumbai v. M/s R.V. Anderson Associates Ltd. clarified the limits of jurisdictional challenges in arbitration and reaffirmed the principles of waiver, acquiescence, and minimal judicial interference under the Arbitration and Conciliation Act, 1996 (“A&C Act”). The Court held that a party which actively participates in arbitral proceedings and raises objections to the constitution of the tribunal only at a belated stage cannot subsequently invalidate the proceedings on jurisdictional grounds. Emphasising Section 4 and Section 16 of the A&C Act, the Court ruled that parties cannot reserve a jurisdictional objection as a strategic device after having acquiesced in the arbitral process. The decision reinforces the doctrinal framework that arbitration proceedings must not be disrupted by belated technical objections after substantial participation by the parties.
The dispute arose out of a consultancy agreement executed in 1995 between the Municipal Corporation of Greater Mumbai (“MCGM”) and M/S R.V. Anderson Associates Ltd., in relation to a World Bank-funded project to upgrade sewerage operations and maintenance services in Mumbai. The agreement provided for a multi-stage project with a duration of seventy-two months. After the work was completed and a final report was submitted in June 2001, disputes emerged regarding payment of outstanding dues owed to the Respondent consultancy firm.
Following unsuccessful discussions between the parties, arbitration was invoked in August 2005 under the dispute-resolution clause in the agreement. Each party appointed a nominee arbitrator in accordance with Clause 8.3(b) of the contract. Initial attempts to explore conciliation and mediation resulted in the arbitration proceedings being kept in abeyance for a period. When settlement efforts failed, the nominee arbitrators appointed a presiding arbitrator to constitute the tribunal.
The appointment process underwent several changes following the resignations of different presiding arbitrators. Eventually, Mr. Anwarul Haque was appointed as the presiding arbitrator, and a preliminary meeting of the tribunal was held in January 2009, with participation from both parties. Only after the commencement of proceedings did MCGM raise an objection to the tribunal’s jurisdiction, alleging that the appointment of the presiding arbitrator was invalid because it had not been made by the Secretary General of the International Centre for Settlement of Investment Disputes (“ICSID”) after the expiry of the thirty-day period contemplated under the contract.
The arbitral tribunal rejected this objection in a Section 16 order and subsequently issued a final award in favour of the Respondent in June 2010. The award was challenged before the Bombay High Court under Section 34 of the A&C Act and later under Section 37. Both challenges were rejected. MCGM then approached the Supreme Court, contending that the tribunal had been improperly constituted and therefore lacked jurisdiction.
The principal issue before the Supreme Court was whether the arbitral award could be set aside on the ground that the tribunal had been improperly constituted due to the delayed appointment of the presiding arbitrator. A related question concerned whether a party that had participated in the arbitral process without a timely objection could subsequently raise a jurisdictional challenge based on alleged non-compliance with the arbitration agreement.
A bench comprising Justices J.K. Maheshwari and Atul S. Chandurkar dismissed the appeal and upheld the arbitral award. The Court held that the interpretation adopted by the tribunal and the High Court regarding the arbitration clause was reasonable and did not warrant interference under Section 34 or Section 37 of the A&C Act.
The Court first examined Clause 8.3(b) of the agreement, which provided that the two party-appointed arbitrators would jointly appoint a presiding arbitrator within thirty days. If they failed to do so, either party could request that the Secretary-General of ICSID make the appointment.
The Court held that this provision was enabling rather than restrictive. It merely created a contingency mechanism allowing the parties to approach ICSID if the arbitrators were unable to reach a consensus. It did not extinguish the co-arbitrators’ authority to appoint the presiding arbitrator after the 30-day period. Since neither party had invoked the ICSID mechanism, the appointment made by the co-arbitrators could not be considered invalid.
The Court further noted that the tribunal’s interpretation of the contractual clause was a plausible one. In arbitration jurisprudence, an arbitral tribunal is the master of contractual interpretation, and courts exercising jurisdiction under Sections 34 or 37 should not substitute their own interpretation merely because another view may be possible.
A central aspect of the Court’s reasoning concerned MCGM’s conduct during the arbitral process. The record revealed that MCGM had been aware of the appointment of the presiding arbitrator on several occasions but did not object at the earliest stage. It also participated in the tribunal’s preliminary meeting without challenging its composition.
The Court observed that the objection to the tribunal’s jurisdiction was raised only after the proceedings had substantially progressed. Such conduct demonstrated acquiescence in the arbitral process. The Court emphasised that the legislative policy underlying Section 4 of the A&C Act discourages parties from remaining silent during proceedings and subsequently challenging the process after an unfavourable outcome.
In support of this reasoning, the Court relied on Hindustan Construction Co. Ltd. v. Bihar Rajya Pul Nirman Nigam Ltd., where the doctrine of waiver in arbitration was discussed in detail. The earlier decision emphasised that parties cannot remain silent during proceedings and later attempt to reopen the process through belated objections. The Court also referred to Quippo Construction Equipment Ltd. v. Janardan Nirman Pvt. Ltd. and Narayan Prasad Lohia v. Nikunj Kumar Lohia, which recognise that challenges to the composition of the tribunal must be raised within the procedural framework prescribed under Section 16.
Although the Court acknowledged that the jurisdictional challenge had technically been raised within the timeline permitted by Section 16(2), it held that the prior conduct of the party remained a relevant consideration in evaluating the merits of the challenge. The extensive participation of MCGM in the proceedings without protest demonstrated its understanding of the contractual mechanism and undermined its later jurisdictional objection.
The Court cautioned against allowing parties to keep a “jurisdictional ace” in reserve and deploy it strategically after the arbitration has progressed. Such tactics, the Court noted, would undermine the efficiency and credibility of arbitration as an alternative dispute resolution mechanism.
Permitting belated objections would enable parties to disrupt arbitral proceedings and defeat the objective of finality that underpins the A&C Act. Arbitration depends on procedural discipline and timely objections, and the courts must guard against attempts to derail the process through technical challenges raised at a later stage.
The Supreme Court ultimately dismissed the appeal and affirmed the validity of the arbitral award. It held that the tribunal was properly constituted and that the arbitrators’ interpretation of the appointment mechanism was reasonable and consistent with the contractual scheme.
More importantly, the Court clarified that jurisdictional challenges cannot be used as an afterthought by parties that have actively participated in arbitration proceedings. Even where a statutory waiver under Section 4 may not strictly apply, the parties’ conduct and acquiescence remain relevant in assessing the legitimacy of such objections.
The ruling carries significant implications for arbitration practice in India. It reinforces the principle that arbitration proceedings should not be destabilised by belated technical challenges to the tribunal’s composition. By emphasising waiver, party conduct, and the limited scope of judicial review under Sections 34 and 37, the judgment strengthens procedural certainty and discourages dilatory tactics in arbitration.
For the Indian arbitration regime, the decision reaffirms the judiciary’s commitment to upholding arbitral autonomy and maintaining the efficiency of the arbitral process. Parties are expected to raise jurisdictional objections promptly and may not strategically invoke them after participating in the proceedings without protest. This approach advances the broader objective of promoting arbitration as a reliable and effective mechanism for commercial dispute resolution in India.
Copyright© 2026 Milon K. Banerji Centre for Arbitration Law instituted at NALSAR University of Law, Hyderabad. All rights reserved.